[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384549":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384549,165,1,"单选题","项目经理认为到目前为止的费用在某种程度上是项目将发生的剩余工作所需成本的指示器，则EAC的公式为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","EAC＝ACc－I－(BAC－EV)\u002FCPIc",true,{"key":16,"text":17,"correct":18},"B","EAC＝ACc＋ETC",false,{"key":20,"text":21,"correct":18},"C","EAC＝AC＋BAC－EV",{"key":23,"text":24,"correct":18},"D","EAC＝ACc＋EV","若到目前为止的费用在某种程度上是项目将发生的剩余工作所需成本的指示器，即当前的偏差被看作是可代表未来偏差的典型偏差时，EAC＝ACc＋ ((BAC－EV)\u002FCPIc)。选项B没有明确ETC的估算方法，选项c假定严格按预算执行的情况下才成立，选项D的公式本身是错误的",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]