[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384548,165,1,"单选题","甲公司生产急需5000个零件，承包给乙工厂进行加工，每个零件的加工费预算为20元，计划2周（每周工作5天）完成。甲公司负责人在开工后第9天早上到乙工厂检查进度，发现已完成加工3600个零件，支付款项81000元。经计算（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该项目的费用偏差为-18000元",false,{"key":16,"text":17,"correct":14},"B","该项目的进度偏差为-18000元",{"key":19,"text":20,"correct":14},"C","该项目的CPI为0.80",{"key":22,"text":23,"correct":24},"D","该项目的SPI为0.90",true,"本题给定了总预算为20*5000=100000元，总工期是10个工作日。要求运用挣值分析法，计算累计到第8个工作日的费用偏差、进度偏差、成本绩效指数、进度绩效指数情况。费用偏差：CV=EV-AC=3600*20-81000=-9000进度偏差：SV=EV-PV=3600*20-5000*20*8\u002F10=-8000CPI=EV\u002FAC=3600*20\u002F81000=0.9SPI=EV\u002FPV=3600*20\u002F（5000*20*8\u002F10）=0.9D是正确的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]