[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384547,165,1,"单选题","挣值管理是一种综合了范围、时间、成本绩效测量的方法，通过与计划完成的工作量、实际挣得的收益、实际的成本进行比较，可以确定成本进度是否按计划执行。下图中标号所标示的区间依次应填写 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①进度落后②成本差CV③进度差SV",false,{"key":16,"text":17,"correct":14},"B","①成本差CV②进度差SV③进度落后时间",{"key":19,"text":20,"correct":21},"C","①进度差SV②成本差CV③进度落后时间",true,{"key":23,"text":24,"correct":14},"D","①进度落后②进度差SV③成本差CV","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]