[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384519,165,1,"单选题","以下关于工作包的描述，正确的是 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可以在此层面上对其成本和进度进行可靠的估算",true,{"key":16,"text":17,"correct":18},"B","工作包是项目范围管理计划关注的内容之一",false,{"key":20,"text":21,"correct":18},"C","工作包是WBS的中间层",{"key":23,"text":24,"correct":18},"D","不能支持未来的项目活动定义","工作分解结构（WBS）详细地说明了项目的范围，详细描述了项目所要完成的工作。WBS的组成元素有助于项目干系人检查项目的最终产品。WBS的最低层元素是能够被评估的、可以安排进度的和被追踪的。 WBS的最低水平的工作单元被称为工作包，它是定义工作范围、定义项目组织、设定项目产品的质量和规格、估算和控制费用、估算时间周期和安排进度的基础。 项目活动的定义正是从WBS的工作包分解而来。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]