[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384514,165,1,"单选题","某公司的项目审查委员会每个季度召开会议，审查所有预算超过一千二百万元的项目。李工最近被提升为该公司高级项目经理，并承担了最大的项目之一，即开发下一代计算机辅助生产流程系统，审查委员会要求李工在下次会议上说明项目的目标、工作内容和成果，为此李工需要准备的文件是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目章程",false,{"key":16,"text":17,"correct":14},"B","产品阐述",{"key":19,"text":20,"correct":21},"C","范围说明书",true,{"key":23,"text":24,"correct":14},"D","工作分解结构","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]