[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384510,165,1,"单选题","项目的工作分解结构（WBS）是管理项目范围的基础，在进行项目工作分解的时候，一般要遵从以下几个步骤： ① 识别和确认项目的阶段和主要可交付物； ② 确认项目主要交付成果的组成要素； ③ 分解并确认每一组成部分是否分解得足够详细； ④ 核实分解的正确性。 这几个步骤中正确的操作顺序应该是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":18},"B","①③②④",true,{"key":20,"text":21,"correct":14},"C","①③④②",{"key":23,"text":24,"correct":14},"D","①④③②","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]