[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384505,165,1,"单选题","某项目经理在生成WBS时，按照（）方法将项目分解为“需求分析、方案设计、实施准备、测试和验收”等几个过程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","子项目",false,{"key":16,"text":17,"correct":14},"B","工作任务",{"key":19,"text":20,"correct":21},"C","生命周期",true,{"key":23,"text":24,"correct":14},"D","可交付物","分解就是把项目可交付成果分成较小的、便于管理的组成部分，直到工作和可交付成果定义到工作细目水平。使用项目生命周期的阶段作为分解的第一层，而把项目可交付物安排在第二层，题干中的信息说明了一个典型的信息系统的生命周期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]