[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384504,165,1,"单选题","在创建WBS时，（ ）是不恰当的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","把项目生命周期的各阶段作为分解的第一层，交付物安排在第二层",false,{"key":16,"text":17,"correct":14},"B","把项目的重要交付物作为分解的第一层",{"key":19,"text":20,"correct":14},"C","把子项目安排在第一层",{"key":22,"text":23,"correct":24},"D","把项目中的各类资源安排在第一层",true,"分解WBS结构的方法至少有如下三种。（1）使用项目生命周期的阶段作为分解的第一层，而把项目可交付物安排在第二层。（2）把项目重要的可交付物作为分解的第一层。（3）把子项目安排在第一层，再分解子项目的WBS。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]