[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384500,165,1,"单选题","某项目的项目经理在进行项目范围变更时，在对项目的技术和管理文件做了必要的修改后，他下一步应该 （ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","及时通知项目干系人",true,{"key":16,"text":17,"correct":18},"B","修改公司的知识管理系统",false,{"key":20,"text":21,"correct":18},"C","获取客户的正式认可",{"key":23,"text":24,"correct":18},"D","获得政府认可","变更完成后，需要进行变更确认，但确认之前得先要通知项目干系人，故答案A正确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]