[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384499,165,1,"单选题","在某信息化项目建设过程中，客户对于最终的交付物不认可，给出的原因是系统信号强度超过用户设备能接受的上限。如果客户对于项目文件中的验收标准有异议，而项目内所有工作流程均无问题，则可能是 （ ） 环节出了问题。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量控制",false,{"key":16,"text":17,"correct":14},"B","WBS分解过程",{"key":19,"text":20,"correct":14},"C","变更控制",{"key":22,"text":23,"correct":24},"D","范围确认",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]