[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384489,165,1,"单选题","在某项目进行的第三个月，累计计划费用是25万元人民币，而实际支出为28万元，以下关于这个项目进展的叙述，正确的是 （） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提供的信息不全，无法评估",true,{"key":16,"text":17,"correct":18},"B","由于成本超支，项目面临困难",false,{"key":20,"text":21,"correct":18},"C","项目将在原预算内完成",{"key":23,"text":24,"correct":18},"D","项目计划提前","本题考查项目的成本管理。 根据成本控制的方法，本题所给参数不全，无法判断是否超出预算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]