[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384485":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384485,165,1,"单选题","项目经理在对所负责项目检查时发现，项目的CPI=0.8，SV=-3 600元，则说明项目的绩效是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目成本超支，进度提前",false,{"key":16,"text":17,"correct":18},"B","项目成本超支，进度延后",true,{"key":20,"text":21,"correct":14},"C","项目成本节约，进度提前",{"key":23,"text":24,"correct":14},"D","项目成本节约，进度延后","CPI\u003C1，SV\u003C0说明此时项目成本超支，进度延误。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]