[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384476":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384476,165,1,"单选题","下列关于工作分解结构（WBS）的叙述中，错误的是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理在分解结构时，严格地将一个工作单元隶属于某个上层工作单元，完全避免交叉从属",false,{"key":16,"text":17,"correct":14},"B","项目管理部依照项目经理分解的WBS进行项目成本估算，但最后发现成本超过预计投资",{"key":19,"text":20,"correct":14},"C","项目经理将项目管理工作也编制成为WBS的一部分",{"key":22,"text":23,"correct":24},"D","项目经理在执行某复杂项目时，在项目开始阶段一次性将项目分解成为精确的WBS，最后按计划完成了任务，受到领导好评",true,"选项A、B、C的叙述均适当，而选项D的叙述是错误的。根据“滚动式计划”方法，WBS的分解也是渐进明细的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]