[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384475":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384475,165,1,"单选题","下列做法无助于缩短活动工期的是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投入更多的资源以加快活动进程",false,{"key":16,"text":17,"correct":14},"B","减小活动范围或降低活动要求",{"key":19,"text":20,"correct":14},"C","通过改进方法或者技术提高生产率",{"key":22,"text":23,"correct":24},"D","用甘特图法",true,"选项A、B、C均属于进度压缩技术，而选项D不属于。选项D无助于缩短活动工期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]