[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384474,165,1,"单选题","在工程网络计划中，工作 M 的最早开始时间为第 16 天，其持续时间为 5 天。该工作有三项紧后工作，他们的最早开始时间分别为第 25 天、第 27 天和第 30 天，最迟开始时间分别为第 28 天、第 29 天和第 30 天。则工作 M 的总时差为()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","9","M 活动的早开始日期(ES)=16天，最早结束日期(EF)=21天；使用逆推法计算最迟结束日期 (LF)=28天，开始日期(LS)=28—5=23 天。总时差=LS—ES 或 LF—EF总时差=23—16=7 天因此选C。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]