[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384472,165,1,"单选题","某信息系统集成项目经理王某收到客户的最新变更要求，他带领其团队成员经过认真分析，发现这次变更将导致项目范围增加近70%，初步估计成本将增加5倍。王某必须要在已被批准的项目计划中改变原定的开始和结束日期，那么他的第一步工作应该是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","修改合同",false,{"key":16,"text":17,"correct":14},"B","增加人员和资源",{"key":19,"text":20,"correct":14},"C","重新制订基准计划",{"key":22,"text":23,"correct":24},"D","采用一个新的目标进度计划",true,"假定项目经理王某已经把这次变更的后果告知了客户，并且客户已经同意了变更，那么他在管理变更后的范围及成本后、应“D．采用一个新的目标进度计划”，再“C．重新制订基准计划”提交客户认可。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]