[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384471,165,1,"单选题","已知网络计划中工作Ｍ有两项紧后工作，这两项紧后工作的最早开始时间分别为第12 天和第15 天，工作Ｍ的最早开始时间和最迟开始时间分别为第6天和第8天。如果工作Ｍ的持续时间为4 天。则工作Ｍ总时差为 （ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","这个题目干扰比较多，一定要抓住概念，总时差是不影响总工期的余量时间，自由时差才是不影响后续活动的余量时间。总时差的计算公式是：总时差=LS（最晚开始时间）-ES（最早开始时间）=2",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]