[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384469":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384469,165,1,"单选题","在制订项目进度计划过程中，（）可以根据有限的资源对项目进度进行调整，是一种结合了确定性与随机性的一种方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键链方法",true,{"key":16,"text":17,"correct":18},"B","专家评估方法",false,{"key":20,"text":21,"correct":18},"C","假设情景方法",{"key":23,"text":24,"correct":18},"D","资源平衡方法","关键链法是另一种进度网络分析技术，可以根据有 限的资源对项目进度表进行调整。关键链法结合了确定性与随机性办法。开始时，利用进度模型申活动持续时间的非保守估算，根据给定的依赖关系与制约条件来绘 制项目进度网络图，然后计算关键路线。在确定关键路线之后，将资源的有无与多寡情况考虑进去，确定资源制约进度表。这种资源制约进度表经常改变了关键路 线。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]