[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384468":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384468,165,1,"单选题","某系统集成企业为做好项目风险管理，给风险定义了3个参数。①风险严重性：指风险对项目造成的危害程度；②风险可能性：指风险发生的几率； ③风险系数：是风险严重性和风险可能性的乘积。 其中，对项目进度延误、工作量偏差的风险严重性等级和风险可行性等级如下表所示：假定该企业将风险系数大于等于6的情况定义为红灯状态，需要优先处理，则下列（）的情况属于红灯状态。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度延误15%，工作量偏差15%，发生几率为0.5",false,{"key":16,"text":17,"correct":14},"B","进度延误15%，工作量偏差35%，发生几率为0.2",{"key":19,"text":20,"correct":21},"C","进度延误25%，工作量偏差15%，发生几率为0.4",true,{"key":23,"text":24,"correct":14},"D","进度延误15%，工作量偏差25%，发生几率为0.4","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]