[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384467,165,1,"单选题","在项目实施期间的某次周例会上，项目经理向大家通报了项目目前的进度。根据以下表格特征，目前的进度 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提前计划7%",false,{"key":16,"text":17,"correct":14},"B","落后计划15%",{"key":19,"text":20,"correct":21},"C","落后计划7%",true,{"key":23,"text":24,"correct":14},"D","提前计划15%","PV=20000+30000+50000=100000EV=20000*0.9+30000*0.9+50000=93000SPI=93000\u002F100000=0.93因为SIP\u003C1所以进度落后，（1-0.93）*100%=7%故答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]