[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384463,165,1,"单选题","某工程建设项目中各工序历时如下表所示，则本项目最快完成时间为 （ ） 周。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","9",{"key":19,"text":20,"correct":14},"C","12",{"key":22,"text":23,"correct":24},"D","13",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]