[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384458":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384458,165,1,"单选题","某研发项目由于很多技术细节不是特别清晰，所以在制定研发项目的进度计划时应该采用（ ）来制定进度计划",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键链法",true,{"key":16,"text":17,"correct":18},"B","关键路径法",false,{"key":20,"text":21,"correct":18},"C","资源平衡法",{"key":23,"text":24,"correct":18},"D","资源日历","关键链法它可以根据有限的资源对项目进度表进行调整。在确定了关键路线之后，将资源的有无与多寡考虑进去，确定资源制约进度表，并增加了持续时间缓冲段，这些持续时间缓冲段属于非工作计划活动",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]