[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384457":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384457,165,1,"单选题","某软件项目已经到了测试阶段，但是由于用户订购的硬件设备没有到货而不能实施测试。这种测试活动与硬件之间的依赖关系属于（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","强制性依赖关系",false,{"key":16,"text":17,"correct":14},"B","直接依赖关系",{"key":19,"text":20,"correct":14},"C","内部依赖关系",{"key":22,"text":23,"correct":24},"D","外部依赖关系",true,"项目管理团队在确定活动先后顺序的过 程中，要明确哪些依赖关系属于外部依赖关系。外部依赖关系涉及项目活动和非项目活动之间关系的依赖关系。例如，软件项目测试活动的进度可能取决于来自外部 的硬件是否到货；施工项目的场地是否平整，可能要在环境听证会后才能动工。活动排序的这种依据可能要依靠以前性质类似的项目历史信息，或者合同和建议。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]