[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384453":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384453,165,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，链接顶点的边表示包含的活动，变色数字表示活动的持续时间（天）。完成该项目的最少时间为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":18},"B","18",true,{"key":20,"text":21,"correct":14},"C","20",{"key":23,"text":24,"correct":14},"D","21","从开始节点到结束节点，持续时间最长的路径是项目的工期，也就是完成项目最少需要的时间，图中Start-B-C-E-F-Finish，持续时间最长为18天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]