[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384447,165,1,"单选题","某项目中有两个活动单元：活动一和活动二，其中活动一开始后活动二才能开始。能正确表示这两个活动之间依赖关系的前导图是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","见图A",false,{"key":16,"text":17,"correct":14},"B","见图B",{"key":19,"text":20,"correct":21},"C","见图C",true,{"key":23,"text":24,"correct":14},"D","见图D","本题考查对活动排序技术和方法的理解。 《系统集成项目管理工程师教程》的“活动排序所采用的主要方法和技术”节中介绍了前导图的含义及使用方法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]