[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384446":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384446,165,1,"单选题","项目可通过分解划分为若干个活动，项目经理通过对项目的网络图进行计算分析后发现一个重要活动X的总时差为2天，自由时差为1天，下列解释最恰当的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期与活动X的总时差无关",false,{"key":16,"text":17,"correct":18},"B","工期受活动X的影响，活动X可以推迟2天都不会影响总工期",true,{"key":20,"text":21,"correct":14},"C","工期受X活动的影响，影响总工期的时间为1天",{"key":23,"text":24,"correct":14},"D","工期受活动X的影响，影响总工期的时间不能确定","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]