[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384444,165,1,"单选题","项目经理小李对某活动工期进行估算时，发现人员的熟练程度和设备供应是否及时对工期至关重要。如果形成最有利组合时，预计17天可以完成；如果形成最不利组合时，预计33天可以完成，按照公司的正常情况，一般22天可以完成该项目的工期可以估算为（ ） 天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":18},"B","23",true,{"key":20,"text":21,"correct":14},"C","24",{"key":23,"text":24,"correct":14},"D","25","本题考查PERT（计划评审技术）：根据公式：PERT估算的活动历时均值=（悲观估计值+4×最可能估计值+乐观估计值）\u002F6，估计该项目完成的时间为（17+4×22+33）\u002F6=23天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]