[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384436":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384436,165,1,"单选题","下列 （ ） 做法不属于进度压缩。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","某项目经理发现项目工期延后，于是开始让项目组成员开始加班加点，提高加班工资，以期待能在规定时间内完成项目",false,{"key":16,"text":17,"correct":14},"B","某项目经理发现项目组成员由于对技术的掌握不熟练，造成进展缓慢，延误工期，于是指派了有经验的人员帮助完成",{"key":19,"text":20,"correct":14},"C","为了节省时间，在需求设计还没有完成时，项目经理就通知组内编程人员开始编写代码",{"key":22,"text":23,"correct":24},"D","项目经理启用应急时间来增加一些项目时间",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]