[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384435,165,1,"单选题","某活动的工期采用三点估算法进行估算，其中最悲观估算是23天，最乐观估算是15天，最可能的估算是19天，则该活动的历时大致需要 （ ） 天",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","19",true,{"key":16,"text":17,"correct":18},"B","23",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","20","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]