[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384430":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384430,165,1,"单选题","已知网络计划中工作M有两项紧后工作，这两项紧后工作的最早开始时间分别为第12天和第15天，工作M的最早开始时间和最迟开始时间分别为第6天和第8天，如果工作M的持续时间为4天，则工作M总时差为()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","在任何网络路线上，进度灵活余地的大小由最早与最迟日期两者之间正的差值决定，该差值叫做“总时差”，M总时差=8-6=2。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]