[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384428,165,1,"单选题","如果挣值EV是300万元，实际成本AC是350万元，计划值PV是375万元。进度执行指数显示（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","仅以原始计划速率的86%进行项目",false,{"key":16,"text":17,"correct":14},"B","正在以原始计划速率的93%进行项目",{"key":19,"text":20,"correct":14},"C","正在以原始计划速率的107%进行项目",{"key":22,"text":23,"correct":24},"D","仅以原始计划速率的80%进行项目",true,"SPI=EV\u002FPV=300\u002F375=0.8=80% 即仅以原始计划速率的80%进行项目",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]