[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384427,165,1,"单选题","某活动的工期采用三点估算法进行估算，其中最悲观估算是19天，最乐观估算是9天，最可能的估算是11天，则该活动的历时大致需要12天，该活动历是方差大概是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.5",false,{"key":16,"text":17,"correct":18},"B","1.68",true,{"key":20,"text":21,"correct":14},"C","1.9",{"key":23,"text":24,"correct":14},"D","2","●期望时间（PERT值）=(最悲观时间+4×最有可能时间+最乐观时间)\u002F6 =（9+4×11+19）\u002F6=12（天） ●标准差（σ）=(最悲观时间?最乐观时间)\u002F6 =（19-9）\u002F6≈1.68（天）",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]