[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384426":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384426,165,1,"单选题","某项目发生了进度延误，于是项目经理在项目关键路径上增加了资源，但是工期仍然未能有效缩短，其可能的原因是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","关键活动的历时总是固定不变的",false,{"key":16,"text":17,"correct":14},"B","关键活动所配置的资源数量总是充足的",{"key":19,"text":20,"correct":14},"C","关键路径上的活动是不依赖于资源的",{"key":22,"text":23,"correct":24},"D","资源的增加可能会导致额外问题的产生从而降低效率",true,"很明显，选项A、B、C是明显错误的。选项D，比如增加新的人员而导致冲突，进而降低效率。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]