[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384423":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384423,165,1,"单选题","进度报告是实施项目进度控制的一个主要工具，在进度报告中可不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际开始与完成日期",false,{"key":16,"text":17,"correct":18},"B","项目例会的时间",true,{"key":20,"text":21,"correct":14},"C","未完成计划活动的剩余持续时间",{"key":23,"text":24,"correct":14},"D","正在进行的计划活动的完成百分比","进度报告中不包括，项目例会时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]