[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384422":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384422,165,1,"单选题","某项目经理绘制的WBS 局部图如下图所示。 B，C工作包的负责人对人日数进行了估算，依据他们的估算结果，项目经理得出了分项工程A的人日数结果，他采用的是 （ ）方法。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","类比估算",false,{"key":16,"text":17,"correct":14},"B","自上而下估算",{"key":19,"text":20,"correct":21},"C","自下而上估算",true,{"key":23,"text":24,"correct":14},"D","多方案分析估算","自下而上估算法：首先估算下层每个更具体的工作资源需要，接着将这些估算按照计划活动需要的每一种资源汇集出总量。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]