[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384419,165,1,"单选题","在估算项目中软件开发的工作量时，项目经理按照自己的经验，利用了以下公式：活动历时（软件开发）=5X19XP （P为开发人员的经验系数，19位开发人员的平均工作时间）。该项目经理采用的估算方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","参数估算",true,{"key":16,"text":17,"correct":18},"B","类比估算",false,{"key":20,"text":21,"correct":18},"C","三点估算法",{"key":23,"text":24,"correct":18},"D","专家判断","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]