[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384416":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384416,165,1,"单选题","以下关于项目进度网络图的描述中，正确的是()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","它应该包含项目的全部细节活动",false,{"key":16,"text":17,"correct":14},"B","它是活动排序的输入和制定进度计划的输出",{"key":19,"text":20,"correct":21},"C","前导图法和箭线图法都是绘制项目进度网络图的具体方法",true,{"key":23,"text":24,"correct":14},"D","它仅以图形方式展示项目计划活动及逻辑依赖关系，简单直观","很明显，前导图和箭线图是绘制项目进度网络图的工具。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]