[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384413":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384413,165,1,"单选题","某活动的工期采用三点估算法进行估算，其中最悲观估算是23天，最乐观估算是15天，最可能的估算是19天，则该活动的历时大致需要19天，该活动历时方差大概是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.7",false,{"key":16,"text":17,"correct":18},"B","1.3",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","4","本题考查的是 PERT，这个必须会计算。其实应该是标准差。 教程 P261，活动历时估算：三点估算法， 期望值=（23 4*19 15）\u002F6=19； 方 差=（23-15）\u002F6=1.3",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]