[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384412":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384412,165,1,"单选题","在进行项目活动历时估算时，（）属于参数估算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从以前类似计划活动的实际持续时间为依据来估算",false,{"key":16,"text":17,"correct":18},"B","用需要完成工作的数量乘以完成单位工作所需时间为估算活动时间的依据",true,{"key":20,"text":21,"correct":14},"C","利用有可能的历时估算，最乐观的历时估算和最悲观的历时估算来计算",{"key":23,"text":24,"correct":14},"D","利用以历时信息为依据的专家判断估算","参数估算是利用历史数据和一些变量之间的统计关系，计算活动资源成本或历时。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]