[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384411,165,1,"单选题","以下关于活动资源估算的描述中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","活动资源估算要确定实施项目活动所需资源的使用时间",false,{"key":16,"text":17,"correct":14},"B","活动资源估算过程必须和成本估算过程相结合",{"key":19,"text":20,"correct":21},"C","进行活动排序时需要考虑活动资源估算问题",true,{"key":23,"text":24,"correct":14},"D","企业基础设施资源信息可以用于活动资源估算","活动排序的下一步流程是活动资源估算。进行活动资源估算时需要考虑活动排序问题。据此，选项C的说法有误。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]