[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384409":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384409,165,1,"单选题","关键路经法是利用进度计划网络图所进行的一种分析技术，下面关于关键路经的说法中是正确的（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","网络图中只有一条关键路经",false,{"key":16,"text":17,"correct":14},"B","关键路经上各活动的时间之和最少",{"key":19,"text":20,"correct":14},"C","非关键路经上某活动发生延误后项目总工期必然会发生延误",{"key":22,"text":23,"correct":24},"D","非关键路经上的活动延误时间如果不超过总时差，项目总工期就不会发生延误",true,"本题考查的是关键路径的基本特征，必须要会。 教程P264，一个网络图中，关键路径可能为多条，关键路经上各活动的时间之和最大，非关键路经上某活动发生延误后项目总工期不一定会发生延误。D 选项正确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]