[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384408,165,1,"单选题","如果项目实施进度比计划提前20%，实际成本只用了预算成本的60%，首先应该（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","重新修订季度计划",false,{"key":16,"text":17,"correct":14},"B","给项目团队加薪，开表彰大会",{"key":19,"text":20,"correct":14},"C","重新进行行成本核算",{"key":22,"text":23,"correct":24},"D","找出最初计划产生差别的原因",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]