[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384403":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384403,165,1,"单选题","某公司与客户签订了一个系统集成项目合同，对于项目的范围和完成时间做出了明确的规定。在制定进度计划时，项目经理发现按照估算的活动时间和资源编制的进度计划无法满足合同工期，为了达到合同要求，项目经理不宜采用的方法是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","赶工",false,{"key":16,"text":17,"correct":14},"B","并行施工",{"key":19,"text":20,"correct":14},"C","增加资源投入",{"key":22,"text":23,"correct":24},"D","缩小项目范围",true,"缩短项目工期的方法有赶工、并行施工、增加资源投入、缩小项目范围等技术和手段。但本题目的前提是：对于项目的范围和完成时间都出了明确的规定，都已经写入了合同中，是项目经理无权单独更改的，故答案D是项目经理不宜采用的方法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]