[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384399":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384399,165,1,"单选题","在系统集成工程建设项目的网络计划图中，关键路径是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由图中关键节点组成的路径",false,{"key":16,"text":17,"correct":18},"B","图中总的工作持续时间最长的路径",true,{"key":20,"text":21,"correct":14},"C","图中包含虚箭线且由关键节点组成的路径",{"key":23,"text":24,"correct":14},"D","图中无虚箭线的路径","在网络计划图中，关键节点组成的路径不一定是关键路径。关键路径是自始至终全部由关键工作组成的路径或路径上总的工作持续时间最长的路径。该路径在网络图上 应用粗线、双线或彩色线标注。关键工作是指最迟完成时间与最早完成时间的差值最小的工作，即网络计划图中总时差最小的工作。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]