[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384398":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384398,165,1,"单选题","某公司正在启动一个新的系统集成项目，任命张某为项目负责人，并从多个职能部门抽调人员组成项目团队，采用矩阵式管理模式。张某认识到在这种情况下团队成员对职能经理的配合往往要超过对自己的配合，因此决定请求公司发布一份 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人力资源管理计划",false,{"key":16,"text":17,"correct":14},"B","项目管理计划",{"key":19,"text":20,"correct":21},"C","项目章程",true,{"key":23,"text":24,"correct":14},"D","沟通管理计划","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]