[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384391,165,1,"单选题","在项目整体管理过程中监督和控制项目是一个关键环节，下列不属于监督和控制过程组的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","客户等项目干系人正式验收并接受已完成的项目可交付物的过程",false,{"key":16,"text":17,"correct":18},"B","企业质量管理体系审计",true,{"key":20,"text":21,"correct":14},"C","在管理项目团队时，项目经理与组员就组员情况进行正式交谈",{"key":23,"text":24,"correct":14},"D","编制绩效报告","选项B是企业级行为，选项B不属于项目的监控过程。选项C属于“管理项目团队”这一日常的监控过程。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]