[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384388,165,1,"单选题","以下关于项目管理计划的叙述中， （ ） 是不正确的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目管理范围计划是项目管理团队确认、记录、核实项目范围的指南",false,{"key":16,"text":17,"correct":14},"B","项目管理计划可以是粗略的、非正式的文档",{"key":19,"text":20,"correct":14},"C","项目管理计划是其他知识域中相关分计划的集合",{"key":22,"text":23,"correct":24},"D","项目管理范围计划仅仅是项目经理确认、管理和控制项目范围的指南",true,"项目管理范围计划需要项目管理团队全员参与。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]