[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384386,165,1,"单选题","整体变更控制过程基于项目的执行情况对项目的过程进行控制。以下关于整体变更控制的描述，()是不恰当的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","每一个变更都需要跟踪和确认",false,{"key":16,"text":17,"correct":18},"B","设置多个变更控制委员会",true,{"key":20,"text":21,"correct":14},"C","变更过程需要维持所有基线的完整",{"key":23,"text":24,"correct":14},"D","整体变更控制在不同层次上实施","变更控制委员会，一个就可以。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]