[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384384,165,1,"单选题","通常，项目整体管理变更控制流程是：受理变更申请→（ ）→变更结果追踪与审核",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","接收或拒绝变更→执行变更→变更的整体影响分析",false,{"key":16,"text":17,"correct":14},"B","变更的整体影响分析→执行变更→接收或拒绝变更",{"key":19,"text":20,"correct":14},"C","执行变更→变更的整体影响分析→接收或拒绝变更",{"key":22,"text":23,"correct":24},"D","变更的整体影响分析→接收或拒绝变更→执行变更",true,"通常，变更控制流程是：受理变更申请→变更的整体影响分析→接收或拒绝变更→执行变更→变更结果追踪与审核。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]