[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384383":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384383,165,1,"单选题","通常在（ ）任命项目经理比较合适",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可研过程之前",false,{"key":16,"text":17,"correct":14},"B","签订合同之前",{"key":19,"text":20,"correct":14},"C","招投标之前",{"key":22,"text":23,"correct":24},"D","开始制定项目计划前",true,"整体管理阶段的任务是：制定项目章程——编制项目管理计划——指导和管理项目执行——监督和控制项目工作——整体变更控制——项目收尾。任命项目经理的工作是在制定项目章程的阶段进行的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]